What changes on the FV-1 from Friday?

The Canary government opens the FV-1 section between Guisguey and La Oliva on Friday 20 November 2026. It measures 5.5 kilometres and runs between kilometre points 7+200 and 12+700.

Drivers will find two carriageways with two lanes each, split by a central reservation of about 12 metres. The government gave no time for the opening.

The Consejería de Obras Públicas, Vivienda y Movilidad (the Canary government's department for public works, housing and mobility) expects shorter tailbacks on the approaches to Puerto del Rosario, from the north and from the Tetir area. It also expects safer, smoother traffic.

The announcement says nothing about tolls or registration. It also gives no speed limit for the new section, so drivers should follow the signs on the road.

What does the new road mean for visitors and residents in the south?

The government's stated aim is to link Corralejo and the main northern municipalities with Puerto del Rosario and the airport. That only works once every section is open.

Together with the stretch from La Caldereta that opened in 2023, the autovía now reaches La Oliva. The government gives no dates for the sections around the airport and Puerto del Rosario.

It also expects easier journeys to the island's ports and the ferries to Lanzarote. If you drive north in a hire car, watch the signs at the new junctions closely during the first days.

For residents of La Oliva, the Cabildo de Fuerteventura (the island government) built a separate 2.7-kilometre access road from the FV-1 half junction to Parque Holandés, finished on 27 February 2024. It reportedly cost about 1.8 million euros and should save residents around 7 kilometres.

What does the whole project cost and who is building it?

According to the government, the Puerto del Rosario–La Caldereta project covers 17.5 kilometres of new autovía and six junctions. They are La Caldereta, Guisguey, La Hondura, La Oliva, Antigua and the airport.

It is a variante, or bypass, of the FV-1, FV-3 and FV-2 roads. That puts 10.5 of the 17.5 kilometres in use, going by the figures for the two sections.

The starting budget was 92.1 million euros, and the 2020 contract stood at 92,098,903 euros. After approved changes during construction, the updated price is 100.75 million euros including IGIC tax.

A consortium of OHLA, Construcciones Rodríguez Ramírez and Satocan won the contract, and work began on 22 September 2020. The available information does not give the price for the 5.5-kilometre stretch alone.

Why is this section opening so late?

According to information from 2023, the Guisguey–La Oliva section was due to open in the first quarter of 2024. It now opens almost three years later.

The first section also ran late: in April 2022 the end of 2022 was given, but it opened on 23 March 2023. The government expected an average of 13,000 vehicles a day there and a design speed of 120 km/h.

The government gave no reasons for the latest delay. It only mentions that approved changes raised the price; whether they also moved the date is not stated.

The government did not say whether there will be an opening ceremony or who will attend. At the first section in 2023, Ángel Víctor Torres, head of the Canary government, and Sergio Lloret, president of the Cabildo of Fuerteventura, were present.

When will the whole autovía be finished?

In its current announcement the government gives no dates for the remaining sections. It plans a phased opening to cut traffic on the FV-1, FV-2 and FV-3 and noise in nearby homes.

In 2023 it said the stretch from the airport roundabout to the FV-3 would open in mid-2024. The section around Puerto del Rosario was to come last, because of affected utility lines and services.

Whether that plan still stands is not in the current announcement. Until completion, roadworks and diversions around Puerto del Rosario remain possible.

Further south, the government approved on 28 August 2025 the project for an autovía from the airport to Pozo Negro, costing 215.9 million euros with five years of construction. It was then put out to tender, and Pablo Rodríguez, Consejero de Obras Públicas, Vivienda y Movilidad, and Rosana Melián, director general of road infrastructure, were involved.