CANARY ISLANDS · INFRASTRUCTURE

Port works to 2030: what Puertos Canarios is planning in Agaete, Órzola and Arguineguín

Puertos Canarios, the Canary Islands government's ports body, has set out a batch of works at the quays of the province of Las Palmas under its Marco Estratégico 2026-2030, or 2026-2030 strategic framework. The package was made public on 6 September 2026, as reported by Europa Press and RTVC.

7 September 2026 · By Julia Roca Bethencourt · 5 min.
The harbour of Órzola on Lanzarote, one of the ports in the plan (illustrative)

Photo: Fry72 (Karel Frydrýšek), CC BY-SA 4.0 (Symbolbild).

The plan mixes finished works, sites about to be completed and intentions without a date. What none of the reports carries is a number: no overall investment figure has been published.

What the framework is and who runs it

Puertos Canarios is a public corporate body attached to the regional ministry of public works, housing and mobility, headed by Pablo Rodríguez. It manages the ports under regional competence, that is, those not classed as ports of general state interest. Its managing director is José Gilberto Moreno, who signs the body's official notices.

It should not be confused with the Autoridad Portuaria de Las Palmas, which answers to the Spanish state and runs the province's large commercial ports. They are two separate administrations, with separate budgets and separate works.

According to Telde Actualidad, the 2026-2030 framework is presented as a four-year road map with four aims: raising the network's operational capacity, strengthening maritime connections, adapting port space to new needs, and improving service for passengers, hauliers, fishermen, marina users and port-related businesses.

Agaete: the work passengers will notice most

The port of Agaete carries the most detailed package. The heaviest intervention is to fold the breakwater's stilling basin, the "cuenco amortiguador", into the port esplanades — a physical reorganisation that frees up and tidies working space.

In parallel, Puertos Canarios is finishing construction of a new passenger terminal. Infonorte Digital lists further pieces of the same package: adapting operations to the port protection plans, relocating the fishing facilities, awarding the cafeteria concession, reorganising the car parks along with new parking management, and installing a canopy over the pedestrian route between the current terminal and the boarding terminal.

That canopy and the parking overhaul belong to Agaete, not to Puerto del Rosario, as they have occasionally been attributed. No source consulted gives an opening date for the new terminal.

Fuerteventura, Lanzarote and La Graciosa

On Fuerteventura, the works to extend and improve the commercial and marina basin at Corralejo are described as being completed in these days. At Morro Jable the plan foresees a full reorganisation, with a new passenger terminal, adaptation to port security rules (the ISPS code, known locally as PBIP) and an upgrade of the marina, with a 2027 horizon according to the published information. At Gran Tarajal the investment focuses on renewing the sewage network, updating the electricity supply and adapting operations.

On Lanzarote, the main item is at Órzola: wider esplanades, a reorganised port, a new passenger terminal and a reserved area for fishing. Órzola is the Lanzarote end of the link to La Graciosa, so the work bears directly on island residents and day trippers.

At Caleta del Sebo, on La Graciosa, the plan sets out a phased upgrade of the port surroundings, with resurfacing close to completion. For Playa Blanca and Puerto del Carmen the sources confirm only their inclusion in a short-term investment programme aimed at improving services, with no works, amounts or timetable specified.

Arguineguín: what is done and what is missing

At Arguineguín, in the municipality of Mogán, the reorganisation of the inner dock is due to be finished in the final four months of this year. According to Maspalomas Ahora it is the most advanced intervention of the whole set, and it covers the beautification of the breakwater parapet, the "espaldón", new railings and the asphalting of the quay now known as the Muelle de la Esperanza.

The stated aim is to fit the facilities to three uses sharing the same basin: fishing, port operations and recreational boating. In a small, heavily used harbour, that division of space is the underlying problem.

Further east, at Castillo del Romeral (Santa Lucía de Tirajana), the body has announced dredging of the fishing shelter, but it remains vague: no published budget, no tender and no construction timetable.

What it means for ferry passengers — and what stays unknown

Agaete is the Gran Canaria end of the archipelago's busiest sea link to Tenerife. The Agaete-Santa Cruz de Tenerife route is run by Fred. Olsen Express and Baleària; in the first half of August 2026 the split on that line was 55% to Fred. Olsen and 45% to Baleària, according to Puente de Mando, which also puts Fred. Olsen's traffic on the connection at just over 6,000 passengers and 2,085 vehicles on a peak August day.

At those volumes a covered walkway, orderly car parks and a new terminal are not cosmetic: they are the difference between boarding in order and queuing in the sun. The same applies at Órzola and Caleta del Sebo, where the ferry is not an excursion but everyday transport.

Two gaps remain. The first is money: none of the sources consulted publishes a total for the 2026-2030 framework or budgets for individual works. The second is timing: apart from Arguineguín (final four months of 2026) and Morro Jable (2027), the projects are presented without a fixed calendar, the new Agaete terminal included.

Practical tip: if you travel through Agaete or Órzola in the coming months, allow extra time — car parks and port aprons are being rebuilt and access routes can change at short notice.
Tenders and official notices for these works appear in the "Perfil del Contratante" of Puertos Canarios and in the Boletín Oficial de Canarias (BOC), the most reliable way to see what has actually been awarded.
Caution: there is no officially published total investment for the 2026-2030 framework and no per-work budgets. Any figure circulating without an institutional source should be treated with care.
Nor is there an announced opening date for the new passenger terminal at Agaete, and the dredging of the Castillo del Romeral fishing shelter has neither a tender nor a timetable.

Key facts

  • The package of works was made public on 6 September 2026 (Europa Press, RTVC, Libertad Digital)
  • Puertos Canarios is a public body attached to the regional ministry of public works, housing and mobility; its managing director is José Gilberto Moreno
  • Agaete: stilling basin folded into the esplanades, new passenger terminal in its final phase, pedestrian canopy and reorganised parking (Infonorte Digital, Europa Press)
  • Arguineguín: inner dock reorganisation due in the final four months of 2026, with the espaldón, railings and asphalting of the Muelle de la Esperanza (Maspalomas Ahora)
  • Morro Jable: full reorganisation with a new passenger terminal on a 2027 horizon; Corralejo: commercial and marina basin already improved
  • No overall investment figure for the framework appears in the sources consulted

FAQ

What exactly is the 2026-2030 strategic framework?
It is the investment road map of Puertos Canarios for the ports under regional competence, built on four strands: operational capacity, maritime connections, adapting port space, and better service for passengers, fishermen, hauliers and recreational boating.
How much money is being invested in total?
That is not known. None of the reports on the announcement gives a global figure or budgets for individual works. Until Puertos Canarios or the regional ministry publishes a number, there is no verifiable total.
When will the new passenger terminal at Agaete open?
There is no date. Sources say construction is in its final phase, but none gives an opening day or a target month for entry into service.
Is the port of Puerto del Rosario part of this plan?
No. Puerto del Rosario is a port of general state interest and answers to the Autoridad Portuaria de Las Palmas, not to Puertos Canarios. The Fuerteventura ports in this framework are Corralejo, Morro Jable and Gran Tarajal.
What is planned for Lanzarote and La Graciosa?
At Órzola, wider esplanades, reorganisation, a new passenger terminal and a fishing area; at Caleta del Sebo, a phased upgrade whose resurfacing is close to completion. Playa Blanca and Puerto del Carmen appear in a short-term investment programme with no details published.