What changes for visitors and residents on Tenerife?

For visitors, tenants and owners in the south of Tenerife, the decree brings no duty, no deadline and no application. It targets operators of very large data centres, meaning sites above 10 megawatts.

The decree has an explicit price aim: the sites' heavy power use should not push electricity prices up sharply. Whether that touches tariffs in the Canary Islands, the report does not say.

On 9 June 2026 the Cabildo de Tenerife (the island government) and the firm Bechtle presented a centre for supercomputers and artificial intelligence. So far it is only a proposal: the presentation named no permits, start date or power use, and it is not reported whether the new decree affects the project.

The technical core would be the D-ALiX data centre run by ITER in Granadilla, in the business section of the Parque Científico y Tecnológico (science and technology park) near Cuevas Blancas. Bechtle would put in about 33 million euros and cover the operating deficit for three years.

What did Page say, and why now?

Regional president García-Page said the industry had made great efforts to save water and energy. He also stressed: “The economy must serve the people.”

Page and Sánchez both lead the Socialists, but distance and mutual criticism have marked their relationship for years. The data centre row is the latest case and falls in the campaign ahead of 29 November.

Castilla-La Mancha has its own stake: several data centres are planned in the region in the coming years. Which election takes place on 29 November, the report does not say.

What does the Council of Ministers decree say?

The Council of Ministers (the Spanish government) approved the decree last week, according to the report, which gave no exact date. It tightens the rules on power, water and digital security for new data centres.

The Ministry for Ecological Transition presented the first draft on 27 August 2026. In the final version the decree applies only from 10 megawatts, while the draft covered every site from 1 megawatt.

The duty to use 80% renewable electricity in every single hour stays. Large sites must also secure mostly renewable power through self-consumption and long-term supply contracts.

This applies until Spain's power mix is more than 90% renewable, which is expected in about a decade. New sites get five years to comply if they join the automatic power-reduction system (SRAP).

The catch: in an emergency the grid operator Red Eléctrica de España may cut them off without compensation. With batteries or their own generation, they may keep running.

Who is fighting the decree?

Technology and energy groups reject the decree even in its softened form. They consider the requirements impossible to meet at present, above all the hourly 80% share of renewable power.

The SpainDC association represents 300 firms, including Amazon, Microsoft and Google. Referring to the draft, it warned that planned investment of 66.9 billion euros by 2030 is at risk.

According to the Observatorio Español de Data Centres, Spain has 161 data centres in operation, 24 under construction and 52 in planning. On paper, the approved projects claim 12 gigawatts of grid capacity, but the ministry expects only 3.5 to 4 gigawatts in 2030.

That gap explains why the government speaks of a selection among projects. In a guest article on 18 September 2026, Sánchez wrote that the question is not whether but how data centres are built.

What remains open, and what comes next?

The report did not say when the decree takes effect. It is also unknown whether the government will change the rules again after the elections.

Nobody has said yet whether the Tenerife supercomputer project falls under the new rules. It is a proposal, and neither power use nor start date has been published.

Visitors and residents need do nothing for now. Anyone wanting to follow developments can look in the Spanish state gazette, the BOE, and in announcements from the Cabildo de Tenerife.