What changes now for visitors and residents on Tenerife?

Nothing changes for the public: Teodoro Sosa's pledge brings no new rule, price or deadline. He is the candidate of Primero Canarias-Coalición Canaria (1ºCAN-CC) for the Congreso de los Diputados (the Spanish lower house) in Las Palmas.

Sosa spoke in Fuerteventura, not on Tenerife, which appears only as one of the islands covered by the renewal programme. If the power supply worries you, ask your hotel or landlord.

Tenerife's last total blackout was in July 2020 and lasted more than seven hours. No confirmed total blackout on the island turned up for 2025 or 2026.

The blackout on mainland Spain on 28 April 2025 caused no outage in the Canary Islands. The island grids are isolated and separate from one another.

What exactly is Primero Canarias-CC demanding?

Sosa's party wants the state to replace plants more than 40 years old, as its manifesto sets out. More efficient, renewable and flexible systems would take their place.

In the Congreso, Sosa also wants to press for faster progress on the second tender for the Canary power systems. It was published on 14 July 2026.

Sosa counts nine total blackouts in eight years and calls it “unworthy”. He said key facilities such as seawater desalination plants are also hit.

He spoke at the Las Salinas (El Charco) thermal power plant in Puerto del Rosario, Fuerteventura. With him were Juan José Rodríguez, third on the list for the Congreso, and Nuria Cabrera, the nationalist Senate candidate for Fuerteventura.

Demolition of the El Charco plant has begun, the report says. Puerto del Rosario's Ayuntamiento (town hall) and Fuerteventura's Cabildo (island government) rejected an extension.

They offered public land in Zurita for a new plant. It would stand away from residential areas.

How much capacity has the state already put out to tender?

On 14 July 2026 the Ministry for Ecological Transition (MITECO) launched the second tender for “potencia firme” (guaranteed capacity) on the island systems. It covers 820.5 megawatts and is meant to meet the demand expected in 2031.

Tenerife-La Gomera gets 230.5 megawatts, second only to Gran Canaria with 320. Lanzarote-Fuerteventura gets 95, La Palma 52, El Hierro 10, the Balearic Islands 80, Melilla 32 and Ceuta 1.

The MITECO caps emissions at 550 grams of CO2 per kilowatt hour. In the Canary Islands, units that will be older than 40 years in 2031 are penalised.

New plants must use at least 5% renewable fuel where available. Eligible are new controllable units, new investment in existing units and longer lifetimes.

The procedure is at the draft-decision stage, in public consultation. No award could be found, and the MITECO named neither a budget nor a payment rate.

How much capacity did the first tender bring for Tenerife?

According to Sosa, an earlier tender has been awarded for 500 million euros. It covers nine generating units with 1,000 megawatts on Tenerife, Gran Canaria, Lanzarote and Fuerteventura.

A summary on the Canary government website gives 374.5 megawatts instead. The figures do not match.

Media reports say Tenerife received 370 megawatts in the first round, for 11 new units run by a new operator. That covers about half of the island's demand.

The grid operator Red Eléctrica does not think the awarded capacity is enough to guarantee supply. The ministry asked it to identify possible gaps up to 2031.

In September 2025 the Canary government approved two emergency plants on Tenerife, one of them in the industrial area of Granadilla de Abona. In November 2025 it rejected Endesa's request to shut down 13 outdated diesel units, because supply must be secured first.

Red Eléctrica completed the undersea cable link between Tenerife and La Gomera on 5 February 2026. Renewable generation in the Canary Islands has doubled since 2018, according to the MITECO, and the target is tenfold.

What happens after the 29 November election?

The general election takes place on 29 November 2026, according to the report. Whether Primero Canarias-CC can push its demands through in the Congreso depends on the result.

Nobody has independently confirmed the nine blackouts, and it is open whether the second tender has been awarded. The figures of 500 million euros and 1,000 megawatts also remain unclear.

Sosa named no concrete measure for Tenerife. The second tender targets the demand of 2031, so renewal remains a project of years.