What changes for hire-car drivers in the south?
The Canary Islands government and the Cabildo de Fuerteventura (the island government) were due to open another 5.5 kilometres of the FV-1 on the morning of 20 November 2026. The stretch runs between the Guisguey and La Oliva junctions, from kilometre 7.2 to 12.7.
Visitors in the south get no confirmed time saving from this stretch. Neither the government nor the Cabildo has published a journey time.
The new road is meant to ease traffic in the north, so the approaches to Puerto del Rosario from the north and from the Tetir area should clog up less. According to the government, Corralejo joins the dual carriageway only once the whole route is finished.
The reports mention no toll or registration, and no closures or diversions for the opening. No speed limit has been published, so drivers should follow the signs.
There is no report on the ceremony so far. Neither a time nor a guest list has been published.
How is the new stretch built?
The new stretch has two lanes in each direction. A central reservation about twelve metres wide separates the carriageways.
The hard shoulders measure 2.50 metres on the outside and one metre on the inside. On both sides there are also verges one metre wide.
The first stretch, between La Caldereta and Guisguey, opened in March 2023 and is about five kilometres long. It is designed for 120 km/h, and around 13,000 vehicles a day were expected at the time.
In Spain the FV-1 counts as an autovía, a motorway-style road, not as an autopista. Both have separate carriageways and grade-separated junctions, but an autopista demands stricter access, so “motorway-style” is the more accurate term.
What does the FV-1 cost, and why is it late?
Work began on 22 September 2020, and a joint venture of OHLA, Construcciones Rodríguez Ramírez and Satocan won the contract. It was awarded for €92,098,903 with a construction time of 54 months.
Changes pushed the budget to €100,751,879.70, according to the Canary Islands government. Both sums include IGIC, the Canary Islands sales tax.
A figure of 104.5 million euros after five price changes is also circulating. It cannot be reconciled with the government figures.
In 2023 the government expected the Guisguey to La Oliva stretch in the first quarter of 2024. The opening therefore comes about two and a half years later.
The contract should have ended in early 2025, yet by July 2026 only 89% of the work was done. Found utility lines, traffic diversions, drainage and new road-surface rules explain the changed project; the government gave no reason for the latest delay.
What is still missing on the FV-1?
The whole project covers 17.5 kilometres with six junctions: La Caldereta, Guisguey, La Hondura, La Oliva, Antigua and the airport. At the airport a roundabout is meant to link the dual carriageway with the FV-2.
The stretch at the airport and around Puerto del Rosario is not finished. The government names no dates for it.
The only estimate comes from a July 2026 report, which says the project will not be finished until well into 2027. At that time the environmental permit for the changed project was still missing.
There is no new dual carriageway for journeys from the airport southwards. The sections towards Pozo Negro, Gran Tarajal (Cuchillete) and Morro Jable are at planning or tender stage.
How far along is the section towards the south?
The Aeropuerto–Pozo Negro section is about 16.8 kilometres long and includes a 1.2-kilometre tunnel. It would be the first tunnel on Fuerteventura.
The government approved the project at the end of August 2025, at around 215.9 million euros and five years of construction. The tender appeared in December 2025 with a base budget of €215,924,834.98.
Four junctions are planned: Aeropuerto (FV-2), El Castillo (FV-413), Las Salinas and Pozo Negro (FV-50). There will also be a 190-metre viaduct over the Barranco de la Torre (a ravine) and three underpasses.
The sources name no confirmed award or start of construction. The FV-1 falls under the roads agreement between the Canary Islands and the state, but no source gives the cost split.