What changes for visitors and residents?

For residents and visitors, nothing changes for now because of the tender. The documents mention no closures, price changes or registration procedures.

The quay will stand on Gran Canaria, not Tenerife, at the Dique Reina Sofía Sur (southern breakwater) of the Puerto de Las Palmas. The documents name no effects for travellers on other islands.

When building starts is open. On 29 July 2026 the central government said work could begin “in the coming months” after the contract is awarded.

Which firms are bidding for the contract?

Ten companies stand behind six bids. According to the tender documents, Sacyr Construcción, FCC Construcción and Dragados each bid alone.

The other three bids come from joint bidding groups (UTE). The first is formed by Rover Infraestructuras, Rover Maritime and Pérez Moreno.

The second consists of Sociedad Anónima Trabajos y Obras (SATO) and Obrascón Huarte Lain (OHL). The third brings together Acciona Construcción Iberia and Lopesan Asfaltos y Construcciones, which the report calls one of the Canaries’ large building firms.

The Autoridad Portuaria de Las Palmas (the port authority) runs the tender. The documents gave no date for the decision.

What exactly will be built at the Dique Reina Sofía Sur?

The quay gets a berthing line of just under 335 metres with a draught of 20 metres, designed for large ships. A second line of 48.73 metres links it to the bend of the existing breakwater.

The job is technically demanding because the crews build in water 35 to 38 metres deep. First they prepare the seabed with a large rock fill as the foundation.

On top they place seven prefabricated reinforced-concrete caissons, each 47.70 metres long and 23.50 metres high. The caissons float to the site, settle on the foundation and are then filled.

Behind the quay, 19,524 square metres of new port area will appear. To make room, the crews adjust the existing road beside the Dique Reina Sofía over 284 metres.

The fittings include bollards for heavy loads, fenders for mooring and pipes for water and fire protection. There will also be power ducts and three lighting masts, each 25 metres high.

Who pays the 45.3 million euros?

Public money pays: the quay belongs to the 2025 to 2029 investment plan of Puertos del Estado (the state port authority) for this port. The plan, approved in 2025, moves more than 350 million euros, according to the central government.

In the plan, 286 million euros for infrastructure is the largest item. A further 41.5 million goes to sustainability, almost 15 million to safety, 5.8 million to access routes and 3.3 million to projects linking port and city.

The central government says the quay could receive EU funds. The amount and share are unpublished, and it is unclear whether the funding is confirmed.

Public investment in Canary ports exceeded 1.2 billion euros over the past decade, the central government says. In the Horizonte 2030 programme, the Canaries rank fifth among the regions with more than 600 million euros.

How does the quay fit with other port projects?

The extension of the Dique Nelson Mandela in the Puerto de La Luz has been finished since 19 December 2025. It adds 262 metres of quay, cost more than 25 million euros and lets bigger ships berth.

Gustavo Santana, president of Puertos del Estado, and Beatriz Calzada, president of the Las Palmas port authority, spoke at the opening. Transport minister Óscar Puente had announced 7 billion euros for state ports up to 2029 on 6 November 2025.

For Canary ports and airports he named more than 2.1 billion euros. Whether the new quay is part of that sum is not clear from the documents.

What is still open, and what comes next?

The award date, the start of building and the build time all remain open. The research found no notice in the BOE (the Spanish official state gazette) for this tender.

The technical site management is not yet awarded either, and the port authority is waiting on it. Two groups are bidding: Proes Consultores, Estudios 7 and Sociedad de Ingeniería, Servicios del Territorio y Medio Ambiente, and also Applus Norcontrol and Canarias Ingeniería Civil.

Another project at the Muelle Reina Sofía has not yet gone to tender. It is meant to extend the berthing line as far as the Biblioteca del Estado.

Travellers need to do nothing. Anyone who wants to check the bidder numbers can find details in the port authority’s contractor profile and on the Plataforma de Contratación del Sector Público.