Do residents and visitors in the south need to prepare for anything?

Nothing changes for now. The demand made on 25 November by the Grupo Popular (PP) in the Cabildo (island government) brings no new rule, deadline or charge, and only the risk remains, because the Valle de Aridane still hangs on a single power line.

At about 04:10 on 2 November the Guinchos–Valle line failed first, and around 17,600 customers in the valle lost power. At 06:38 all the generating units shut down, and by 10:26 some 50,508 connections across the island were reportedly affected.

None of the sources says how many of those connections were in the south. The cause of the shutdown is also open, because the grid operator Red Eléctrica (REE) has not explained it, according to the information available.

Sources close to the government name a lightning strike as the trigger of the first fault. The sources contain no official advice for visitors or residents.

Anyone booking accommodation in the west can ask the owner whether they have a solution for power cuts. That is practical advice, not an official requirement.

What exactly does the PP accuse the Cabildo of?

Island councillor Carlos Cabrera of the Grupo Popular accuses the island leadership of blocking the second line into the valle through sheer inaction. He says the Las Breñas–Valle de Aridane link has had a project and a budget for more than three years.

According to Cabrera, only the political will is missing to settle the technical details of burying the cable and to sign the final agreement with Red Eléctrica. The information available does not say which details are still open.

Cabrera says the whole west hangs on one supply line, which failed a few days ago. He puts the blame on the island leadership alone, and says the Canary government will take measures to soften the effect of generation outages.

The report does not include the Cabildo's reply. The sources do not make clear whether Cabrera means the 2 November outage.

Who decides on the second line?

The state, through the environment ministry MITECO, and Red Eléctrica as operator are responsible for the transmission grid. The Cabildo does not decide on the line, but it was politically involved in 2017, when La Palma rejected a route over the mountain ridge.

Plans include a new substation at Las Breñas and a second 66-kV line into the valle. Red Eléctrica began the procedure in 2024, and according to the reports it is not yet complete.

On 29 May 2024 the BOE (Spain's official state gazette) published a notice on the construction design, number BOE-B-2024-19576. A notice on an amended design, BOE-B-2026-3191, followed on 5 February 2026.

The amended design provides for a double 66-kV line, partly overhead and partly underground, plus a list of plots to be expropriated. The developer, length, budget and objection deadlines are not visible in the information available, and no source gives a cost or completion date.

What is the state of the geothermal plans?

The PP warns that delays put at risk about 25 million euros that MITECO approved in 2023. No other source could confirm this figure, so for now it stands as a PP claim.

In February 2024 MITECO allocated a total of 106 million euros to the Canary Islands for deep geothermal energy. For La Palma, reports give 48 million euros of public money, which is meant to reach 96 million euros with private funds.

The PP wants the Cabildo to speed up the procedures and set aside its own money for the test drilling, in case outside funds fall short. It also wants to ask the Canary Islands' Consejería de Transición Ecológica (environment department) for funds, and expects to succeed.

Reconstruction commissioner Héctor Izquierdo originally had until 30 June 2026 to submit the geothermal project. MITECO extended the deadlines to December 2028, which the Canary government welcomed.

On 19 October 2026 the Consejo de Gobierno (the Canary government's cabinet) exempted the project “Sondeo Isla de La Palma” from the simplified environmental procedure. The report gives no amounts, start of works or drilling permit.

What next steps are known for the west and the south?

No date has been published for signing the agreement with Red Eléctrica. The Cabildo has also not commented, at least in the report on the PP demand.

One other project matters for the south. In a statement of 1 July 2025, MITECO names a new line between Los Guinchos and Fuencaliente, meant to close the island's ring in the south, but the sources give no date for it.

Endesa runs the Los Guinchos power station with 13 diesel units and about 80 megawatts, and it is more than 30 years old. In May 2025 Fernando González, island councillor for industry and energy, criticised operator and producer for passing the ball to each other.

Only geothermal energy has a dated next step, the deadline of December 2028. No source gives a completion date for the second line into the valle.