What changes for visitors and residents in the south?

The Cabildo statement of 17 November 2026 says nothing about prices, rules, deadlines or applications. It also gives no megawatt, euro or capacity figures and no date.

According to the authorities, the blackout of 3 October 2026 hit Lanzarote and La Graciosa. A power cut on Fuerteventura is not confirmed.

Playa Blanca stayed connected because it is supplied through the link with Fuerteventura, as minister Mariano Hernández Zapata told parliament. The Cabildo asks what would have happened on Fuerteventura if the fault had not cut the two islands apart electrically.

No source says travellers need to do anything. Anyone with a specific concern should ask their hotel or landlord.

What happened on Lanzarote on 3 October?

The power cut began around 05:45 and hit Lanzarote and La Graciosa. According to the authorities' provisional account, it started with a fault in the 66 kV grid at the Mácher substation in Tías.

About four minutes later, a second fault at the San Bartolomé and Punta Grande stations struck during the restart, and generation was lost. About 51,703 customers were affected at first, later around 73,600.

The figure varies by source and time, and one report puts it at about 84,000 customers. Supply was practically restored by around 07:13.

The seawater desalination plants stopped, so water cuts and pressure drops were possible for a time. The pre-alert level of the Canary Islands emergency plan PLATECA applied from 07:15.

The Canary Islands government wants to know what failed and why, and said it would demand accountability. It is analysing the reports from Red Eléctrica (the grid operator) and Endesa, whose content is not known.

What does the Cabildo demand from the Canary Islands government?

President Lola García wants every island to put up the same resources to secure its supply. She says: “If Lanzarote needs emergency reinforcement, the government should install it on Lanzarote.”

Zapata is the Canary Islands government's minister for ecological transition and energy. He told the Parliament of Canarias that the cause was a fault at the Mácher substation, and said Fuerteventura's generation deficit raises the vulnerability of the shared system.

The Cabildo demands that the reports from Red Eléctrica and Endesa be published. It also wants the government to clarify under what conditions the emergency generators on Fuerteventura start up.

For Lanzarote, the government should urgently start a procedure for emergency generators. It should also disclose which proposals and objections it sent to the ministry about Fuerteventura.

What is happening with the plants at La Herradura?

The Canary Islands government presented two temporary plants that Sampol and DISA are installing at La Herradura in Puerto del Rosario. They are meant to make up Fuerteventura's generation deficit.

The Cabildo statement says nothing about their output. Unconfirmed reports say the two together deliver 33 MW, about 60% of an estimated 50 MW deficit.

The start-up date, cost and output are not confirmed by a primary source. Unconfirmed reports say the plants are meant to secure supply in high season.

For context, the Spanish energy ministry MITECO recognises an extra 32.8 MW of controllable capacity for Fuerteventura, according to a press release of 8 August 2025. For Gran Canaria it names 137.8 MW, and for Tenerife 71.6 MW.

Why does the Cabildo care about land and storage?

Nereida Calero, the island councillor for land-use planning, criticises the Canary Islands government for approving energy plants under Article 6 bis, bypassing the island and municipal plans. She says it concerns farmland, protected areas and residents who may have to fear expropriation.

Calero says: “Fuerteventura has the right to decide about its own territory.” According to her, the approved plants did not have to include storage.

She argues that the energy already produced should be put to better use before more land is taken. She names storage, self-consumption and efficiency measures.

The dispute is not new: on 16 March 2026, García and Oswaldo Betancort, president of the Cabildo of Lanzarote, jointly rejected the Canary Islands government's model of Zonas de Aceleración de Renovables (renewables acceleration zones). They fear large energy plants on rural land and do not want renewables at the expense of the territory.

The Cabildo holds to its demand for a substation at Zurita so that the El Charco power plant can be relocated. It still rejects the power link with Gran Canaria.

What happens next?

The Cabildo statement names no next date. No reply from the Canary Islands government to the demands has been found.

The date of Zapata's appearance in parliament and the content of the Red Eléctrica and Endesa reports also remain open. Binding information on start-up and operating conditions for the La Herradura plants would have to come from the Canary Islands government.