If you have passed through Tenerife South – Reina Sofía Airport in recent years, you will have felt it: the buzz of a record-breaking 14 million passengers a year, the queues at peak times, and a terminal that has been bursting at the seams. Now, Aena has officially launched the biggest transformation in the airport's history. The state-owned airport operator has put two major construction contracts out to tender, with a combined value of around €512.6 million. This is the concrete, on-the-ground start of a project that will redefine the gateway to Tenerife for decades to come.
The plan is ambitious but carefully phased. A new, unified terminal area will be created, expanding the building's surface by almost 50%. A multi-storey car park with roughly 2,000 spaces will reorganise the entire landside area. And, looking further ahead, the design is physically prepared to connect seamlessly with a future train line from the south of the island. The most crucial detail for travellers? The airport will not close for a single day during the entire 7 to 8 years of construction.
Decoding the Investment: Why You See Different Figures
You might have seen different numbers in the news – €512 million, "more than €550 million", or even €553.6 million. These are not conflicting reports, but rather different layers of a very large cake. The clearest way to understand it is this: the €512.6 million currently being tendered is for the core construction works. This is split into a €464.1 million contract for the terminal building itself and a €48.4 million contract for the new parking areas and access roads.
The "more than €550 million" figure, consistently used by Aena and local authorities, represents the full cost of the integrated terminal-area programme. This includes the current construction tenders plus additional packages that are not yet tendered, such as a roughly €69 million upgrade for baggage-handling systems and equipment. The €553.6 million figure you may see in official documents is Aena's total planned investment for Tenerife South in the 2027–2031 regulatory period, which is dominated by this project but may also include other airport improvements. In short, the money on the table right now for builders is around €512 million, but the complete vision will cost well over €550 million.
A New Terminal, Step by Step
The heart of the project is a "complete remodelling of the terminal area," as Aena describes it. The current building will undergo a total transformation, integrating existing structures into a modern, unified design. The terminal's surface area will grow by almost 50%, creating significantly more space for check-in halls, security control lines, boarding lounges, and baggage reclaim areas. The goal is not to increase the number of flights – the runway and aircraft apron are not being touched – but to dramatically improve the flow and capacity inside the terminal, targeting a comfortable handling capacity of around 15 to 16 million passengers per year.
To achieve this without disrupting your holiday, the works are broken down into an intricate sequence of 57 sub-phases. The first major phase, lasting about 30 months, focuses entirely on the landside area: building the new multi-storey car park and reconfiguring all access roads. This is a strategic move to free up space in front of the terminal, creating the working area needed for the subsequent, more complex terminal expansion phase, which is estimated to take around 40 months. A final phase will tackle the baggage areas over roughly 56 months. Aena has explicitly stated that closing the airport would allow them to finish in just 2 to 3 years, but that option was ruled out to keep the island connected.
Parking, Pedestrians, and a Future Train
For anyone who has circled the current surface car park in frustration, the parking plan will be a welcome change. The first visible sign of the whole project will be the construction of a two-level parking building over the existing surface lot. This €48 million investment will deliver around 2,000 spaces, with roughly 800 for general public use and 1,200 dedicated to rent-a-car companies. The design aims to reduce traffic chaos in front of the terminal façade and create a much clearer separation between private cars, taxis, and rental vehicles.
Cleverly, the project also looks to a future that is not yet built. The new parking structure includes an elevated pedestrian walkway and an internal corridor designed to lead directly to a planned south Tenerife train station. If the "tren del sur" is eventually built by other authorities, the airport is physically ready. Passengers would enjoy a covered walk of less than ten minutes from the platforms to the terminal. While there is no date for the train, the airport will not need to be dug up again when the time comes.
What This Means for Your Next Trip
Let's be realistic: a construction site of this scale, lasting the better part of a decade, will be noticeable. The airport will stay open and flight operations will continue normally, but your journey through the terminal will evolve. During the early parking phase, expect re-routed access roads and temporary parking arrangements. As work moves inside, check-in desks, security lanes, and boarding gates may be temporarily relocated. You will see construction hoardings, follow provisional signage, and possibly walk slightly longer routes than you remember.
However, the long-term gain is substantial. Once the major phases are complete, you can look forward to a much more spacious, less congested terminal with more shops, restaurants, and comfortable waiting areas. The new parking building will finally offer a proper, modern facility. The key advice for now is to build in a little extra buffer time, check the official Aena app for the latest layout changes before you travel, and pack a little patience. The destination remains the same beautiful island; its front door is simply getting a long-overdue renovation.
Common Questions
- Will Tenerife South Airport close during the works?
- No. The entire project is designed around keeping the airport fully operational. The works are split into 57 sub-phases to maintain capacity.
- When will the construction work actually start?
- Visible construction is expected to begin in late 2027 or early 2028, starting with the new multi-storey car park.
- How long will the whole project take?
- Aena estimates a total construction duration of 7 to 8 years, meaning completion is expected beyond 2031.
- Is the airport building a new runway?
- No. The project focuses exclusively on the terminal building, parking, and landside access. The runway and aircraft apron are not being modified.
- Will there be a direct train to the airport?
- The new terminal and parking building are physically prepared for a future south Tenerife train line, but the construction of the railway itself is a separate project with no confirmed date yet.
Read on
- Tenerife South Airport: arrivals, departures and infoTenerife · 4 October
- Taxi to the airport: a €40 fare cap for Las Palmas de Gran CanariaGran Canaria · 20 August
- When Gran Canaria Doubted Where to Build Its Airport: The Gando StoryGran Canaria · 9 August
- Güímar Paseo Romero 15 Nov: date set, time still unknownTenerife · 29 October
- Buenavista del Norte: Expo Bandas 2026 on 1 NovemberTenerife · 29 October
- All events on Tenerife →
Stand: 31 July 2026. All figures and timelines are based on official Aena announcements and are subject to environmental approvals and final contract awards.